Completed Project

Taronga Zoo Upper Car Park Precinct

Richard Crookes Constructions

(PROJECT VALUE = $1.5 MILLION).

Scope of Work:                       Demolition

                                                Bulk Excavation

                                                Detail Excavation

                                                R.T.A. Road Works

                                                Bored Piers

                                                Slab Preparation

                                                Civil Works

                                                Car-park Construction

Description:

Taronga Zoo is certainly one of the most high profile projects completed to date and was challenging due to the restraints placed on the site with such high traffic and pedestrian volumes. 

 

The site was also listed as of heritage value and great care was required during the initial stages of excavation.

 

Due to the sensitive nature of the area, environmental management was a key objective of the construction process.

 

In total, over 5300m2 of asphaltic pavement was prepared and laid, and over 7,500m2 of concrete slab preparation completed.