EASTERN CREEK WAREHOUSE PROJECT

26/03/2021

The Eastern Creek Warehouse project consists of bulk earthworks, stormwater, detail excavation and various pavement works. On completion, the project will include earthworks steming across a 55,000m2 lot, including over 13,000m3 level 1 supervised cut to fill, 700m of divergent drains, and importation of over 15,000T of sandstone into the job for a 12,500m2 building pad.


Scope of Work:


  • Clear site from all weeds and grubs - 55,000m2 site.
  • Bulk Earthworks - Cut to fill 13,000m3 and stockpile on site.
  • Construct building pad with sandstone - 12,000m2.
  • Pavement Preparation
  • Detail Excavation
  • Stormwater and Drainage
Attcall Civil Contractors material haulage and truck hire

CLIENT

Taylor Construction Group


LOCATION

Eastern Creek


VALUE

2.5 million


STATUS

Current Project


DATE ANTICIPATED

May 2021